A pert project has 45 activities of which 19 are on a critical path. The estimated time for the critical path is 120 days. The sum of all activities variances is 64, while the sum of variances along the activities path is 36. The probability that the project will be completed between 108 and 120 is?
Check your essay before you submit. See exactly what your professor sees.
See your AI and plagiarism results before your instructor does.Get the exact same report your professor uses. Trusted by 50,000+ students worldwide.
- -2.0
- .0227
- .1058
- .4773
- .9773
© BrainMass Inc. brainmass.com March 21, 2019, 4:54 pm ad1c9bdddf
https://brainmass.com/business/business-management/pert-problem-completing-project-between-201773
Solution Preview
Standard deviation for critical path = 36^0.5 = 6
Calculate z value (for standard …