Shirley Hopkins is developing a program in leadership
training for middle-level managers. Shirley has listed a number of
activities that must be completed before a training program of this
nature could be conducted. The activities, immediate predecessors,
and times appear in the accompanying table:
Activity Immediate Predecessors Time (days)
A —– 2
B —– 5
C —– 1
D B 10
E A,D 3
F C 6
G E,F 8
a) Develop an AON network for this problem.
b) What is the critical path?
c) What is the total project completion time?
© BrainMass Inc. brainmass.com March 21, 2019, 11:24 pm ad1c9bdddf
https://brainmass.com/business/business-management/activity-on-node-aon-network-456663
Solution Preview
NEED HELP WRITING AN ESSAY
Tell us about your assignment and we will find the best writer for your project.
Get Help Now!NOTE: PLEASE SEE THE ATTACHED FILE FOR A DETAILED COMPUTATION.
Posting Requirement:
a) Develop an …