The following lists of jobs in a critical department includes estimates of their required times:
Check your essay before you submit. See exactly what your professor sees.
See your AI and plagiarism results before your instructor does.Get the exact same report your professor uses. Trusted by 50,000+ students worldwide.
JOB Required time (days) Days to delivery promise Slack
A 8 12 4
B 3 9 6
C 7 8 1
D 1 11 10
E 10 -10 –
F 6 10 4
G 5 -8 –
H 4 6 2
A. Use the shortest operation time rule to schedule these jobs. What is the schedule? What is the mean flow time?
B. Assume the schedule in “a” is not acceptable for management. Jobs E and G must be done first, for obvious reasons as they are already late. Reschedule and do the best you can while scheduling jobs E and G first and second, respectively. What is the new schedule? what is the new mean flow?