Pleas see the attached case study table and questions to be answered.
Check your essay before you submit. See exactly what your professor sees.
See your AI and plagiarism results before your instructor does.Get the exact same report your professor uses. Trusted by 50,000+ students worldwide.
- Develop a network drawing for Hill Construction and determine the critical path. How long is the project expected to take?
- What is the probability of finish in 270 days.
- If it is neccesay to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimate can be used as crash times
SOUTHWESTERN UNIVERSITY PROJECT
The Estimates (Days)
Activity Description Preccessor(s) Optimistic Most Likely Pessimistic Crash (cost/day)
A. Bonding, insurance, tax structuring ……… 20 30 40 1,500
B. Foundation, concrete footings for boxes A 20 65 80 3,500
C. Upgrading skybox, stadium seating A 50 60 100 4,000
D. Upgrading walkways, stairwells, elevators C 30 50 100 1,900
E. Interior wiring, lathes B 25 50 35 9,500
F. Inspection approvals E 0.1 0.1 0.1 0
G. Plumbing D, E 25 30 35 2,500
H. Painting G 10 20 30 2,000
I. Hardware/AC/metal workings H 20 25 60 2,000
J. Tile/carpeting/windows H 8 10 12 6,000
K. Inspection J 0.1 0.1 0.1 0
L. Final detail work/cleanup I, K 20 25 60 4,500