Shirley Hopkins is developing a program in leadership training for middle-level managers. Shriley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the acconmpaning table:
Activity Immediate Predecessors Time/days
A — 2
B — 5
C — 1
D B 10
E A,E 3
F C 6
G E,F 8

Check your essay before you submit. See exactly what your professor sees.

See your AI and plagiarism results before your instructor does.Get the exact same report your professor uses. Trusted by 50,000+ students worldwide.

a. Develop an AON network for this problem
b. What is the critical path?
c. What is the total project completion time?
d. What is the slack time for each individual activity?

3.15
The following is a table of activities associated with a project at Bill Figg Enterprises, these durations and what activities each must precede:
Activity Duration (weeks) Precedes
A (start) 1 B,C
B 1 E
C 4 F
E 2 F
F (end) 2 —

a. Draw an AON diagram of the project, including activity durations.
b. Define the critical path, listing all critical activities in chronological order.
c. What is the project duration in weeks?
d. What is the slack (in weeks) associated with any and all noncritical paths through the project.
© BrainMass Inc. brainmass.com March 21, 2019, 7:43 pm ad1c9bdddf
https://brainmass.com/business/business-management/drawing-aon-excel-304150
Attachments

Chaper 3 Problems.docx
SOURCE: WWW.ROYALRESEARCHERS.COM
Havent found the Essay You Want?
We Can Help
The Essay is Written From Scratch for You

🛒Place Your Order

ORDER AN ESSAY WRITTEN FROM SCRATCH at : https://royalresearchers.com/
PLACE YOUR ORDER
Share your love