Analogous estimating is generally less costly and less time consuming than other techniques, but it is also less accurate.
Check your essay before you submit. See exactly what your professor sees.
See your AI and plagiarism results before your instructor does.Get the exact same report your professor uses. Trusted by 50,000+ students worldwide.
Analogous duration estimates can be applied to a total project or to
segments of a project and may be used in conjunction with other estimating methods. Analogous estimating is most reliable when the previous activities are similar in fact and not just in
appearance, and the project team members preparing the estimates have the needed expertise.
6.5.2.3 Parametric Estimating
Parametric estimating is an estimating technique in which an algorithm
is used to calculate cost or duration based on historical data and
project parameters. Parametric estimating uses a
statistical relationship between historical data and other variables (e.g., square footage in construction) to calculate an estimate for activity parameters, such as cost, budget, and duration.
Activity durations can be quantitatively determined by multiplying the quantity of work to be performed by labor hours per unit of work. For example, activity duration on a design project is
estimated by the number of drawings multiplied by the number of labor hours per drawing, or on a cable installation, the meters of cable multiplied by the number of labor hours per meter.
For
example, if the assigned resource is capable of installing 25 meters of cable per hour, the duration required to install 1,000 meters is 40 hours. (1,000 meters divided by 25 meters per hour). This
technique can produce higher levels of accuracy depending upon the sophistication and underlying data built into the model. Parametric time estimates can be applied to a total project or to
segments of a project, in conjunction with other estimating methods.
6.5.2.4 Three-Point Estimating
The accuracy of single-point activity duration estimates may be
improved by considering estimation uncertainty and risk. This concept
originated with the program evaluation and review
technique (PERT). PERT uses three estimates to define an approximate range for an activity’s duration: • M ost likely (tM).
This estimate is based on the duration of the activity, given
the resources likely to be assigned, their productivity, realistic expectations of availability for the activity, dependencies on other participants, and interruptions. • Optimistic (tO). The
activity duration based on analysis of the best-case scenario for the activity. • Pessimistic (tP). The activity duration based on analysis of the worst-case scenario for the activity.