6 – PROJECT TIME MANAGEMENT
6.4.3 Estimate Activity Resources: Outputs
6.4.3.1 Activity Resource Requirements
Activity resource requirements identify the types and quantities of resources required for each activity in a work package.
These requirements then can be aggregated to determine the
estimated resources for each work package and each work period. The amount of detail and the level of specificity of the resource requirement descriptions can vary by application area. The
resource requirements documentation for each activity can include the basis of estimate for each resource, as well as the assumptions that were made in determining which types of resources
are applied, their availability, and what quantities are used.
6
6.4.3.2 Resource Breakdown Structure
The resource breakdown structure is a hierarchical representation of resources by category and type.
Examples of resource categories include labor, material, equipment, and supplies. Resource
types may include the skill level, grade level, or other information as appropriate to the project. The resource breakdown structure is useful for organizing and reporting project schedule data
with resource utilization information.
6.4.3.3 Project Documents Updates
Project documents that may be updated include, but are not limited to:
• Activity list, • Activity attributes, and • Resource
calendars.
6.5 Estimate Activity Durations
Estimate Activity
Durations is the process of estimating the number of work periods
needed to complete individual activities with estimated resources.
The key benefit of this process is that it
provides the amount of time each activity will take to complete, which is a major input into the Develop Schedule process. The inputs, tools and techniques, and outputs of this process are
depicted in Figure 6-14. Figure 6-15 depicts the data flow diagram of the process.
©2013 Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Fifth Edition